Friday, September 28, 2007

The Avenue District Hard Hat Tour

A top-to-bottom look at The Avenue District

On Saturday, Sept. 22, 2007, Zaremba hosted The Avenue District Hard Hat Tour for future residents of the walkable neighborhood.

The day started out at 9 a.m. with continental breakfast, and then participants split into two groups – one lead by Matt Zaremba and Site 3 project manager Mike Sathre, and the other by Nate Zaremba, Jr. – to visit both Building One at 1211 St. Clair Ave. and the Site 3 townhomes at Rockwell Avenue and E. 15th Street.

At the townhomes, participants were able to view the inside of a townhome in the drywall phase, as well as get up to the roof to see how the rooftop decks are being constructed.


At 1211 St. Clair Ave., participants first toured the first floor and proceeded down to the basement level. Mark Panzica from Panzica Construction explained how each of the buildings 10 floors would be poured and constructed.

Monday, September 24, 2007

Trend Tracker Links (9.24.07)

Urban Model for the Nation
Washington Post - United States
By Alejandro Lazo
"Christopher B. Leinberger, a visiting fellow with the Brookings Institution, believes the move into urban corridors that is occurring in ..."

University Circle developers announce a high quality short list of ...
Plain Dealer – Cleveland, OH
"A bird's eye view shows the general massing of the Triangle development. Apartments and retail buildings to be built by developers Nathan Zaremba and Richard and Ari Maron are indicated in white, along with new buildings ..."

“Magic” Johnson Introduces Design-Your-Own Lofts in the Bay State
Multi-Housing News
"Earvin “Magic” Johnson and the Canyon-Johnson Urban Fund joined with local partner Cathartes Private Investments, Massachusetts State Treasurer Tim Cahill and students from the Boston Parties in Education program this morning to preview the Mezzo Design Lofts, a workforce housing, Transit-Oriented Development (TOD) in Charlestown, Mass., about a mile outside of Boston…."

Intown living: Sylvan Hills revitalized, yet affordable
Atlanta Journal Constitution - GA
"Kersey is an urban planner who works in Midtown and Kravitz commutes to Decatur where he works for MedShare International, a nonprofit that recovers surplus ..."

Saturday, September 22, 2007

1211 St. Clair Ave. - 2nd Floor Construction Video

Work has progressed to the 2nd floor at 1211 St. Clair Ave. Check out the brief video below taken on Friday, Sept. 21.



The 10-story building, at the intersection of East 12th Street and St. Clair Avenue in downtown Cleveland, will include 50 elegant lofts (floors 3-8), eight penthouses (floors 9-10) and up to 9,000 square feet of retail (floors 1-2).

Thursday, September 13, 2007

Ground-Level Images from Site 1 - Sept. 12

Photos taken from East 12th Street on Sept. 12, 2007 show progress on 1211 St. Clair, future home to 50 elegant lofts, eight penthouses and up to 9,000 square feet of retail space in The Avenue District, downtown Cleveland's premier walkable neighborhood.



Avenue District Townhome Images - Sept. 12

Masonry work continues on the first 10 townhomes in The Avenue District. The rubber roof is now complete, and installation of the rooftop decks is underway.


The plumbing and electric roughs (behind the walls) are completed in most units, with insulation and drywall beginning in select units later this month. Buyers will also finish their interior selections this month, and start moving in this fall.


In addition, grading work has begun on the second townhome building, future site of the next 10 units at Rockwell Avenue and the newly created East 15th Street in downtown Cleveland.

Photos below (taken Sept. 12, 2007) show Building One to the east, with grading work on Building Two in the foreground.


Thursday, September 6, 2007

Masonry Works Begins on Site 3 Townhomes

Masonry work is underway on Site 3 townhomes at The Avenue District, located at Rockwell Avenue and the newly created East 15th Street in downtown Cleveland.


In addition to the masonry skin, the rubber roof is now complete, with installation of the rooftop decks starting later this week. The plumbing and electric roughs (behind the walls) are completed in most units, with insulation and drywall beginning in select units. Buyers will finish their interior selections this month.




Saturday, September 1, 2007

Images from Site 1 - Aug. 31

In the late-afternoon shadows of downtown Cleveland's skyline, The Avenue District's Building One rises at East 12th Street and St. Clair Avenue:




The tower crane stands 254 feet above Site 1 at The Avenue District: